Religious confessions whose relations with the State are governed pursuant to Article 8, paragraph 3 of the Constitution, which have an organized, widespread and consistent presence at the national level and a significant settlement in the local community, may request a regional contribution for the realization of works and interventions on the same buildings.
The procedure involves the identification of contributions with a municipal council decision approving the forecast budget.
 
Time-limits for bringing proceedings: contextual to the approval of the budget, 60 days from the filing of the declaration of commencement of the works, 60 days from the filing of the expense documentation.

City of Bra - Private building office

During the pandemic emergency, access to municipal offices is allowed only by reservation by contacting the references you find HERE



Monday, Wednesday and Friday: 8: 30-12: 30

 

From 2 May 2019:

Monday: 8.45 - 12.45

Wednesday: 8.45 - 12.45

Friday: 8.45 - 12.45

 

These are the detailed planning tools to cater for urban areas or existing areas, identified by the regulatory plan, where space for public use needs to be recovered.

 

What you need: stamp application addressed to the Mayor; project of the intervention in triplicate drawn up by a qualified professional; illustrative and financial technical report prepared by a qualified professional; draft of the implementing rules and, if necessary, draft agreement;

 

costs:

two stamp brands from € 16,00
€ 325,00 payment for secretarial rights

attachments:
Download this file (PEC Convention Pattern.pdf)Conventional PEC.pdf Schema[The convention scheme.]0 kB

City of Bra - Private building office

headquarters: Via Barbacana 6 (fourth floor)
phone: (+ 39) 0172.438356
fax: (+ 39) 0172.44333
mail: urbanistica@comune.bra.cn.it

Manager: Stefano Tealdi
Responsible: Bruno Parizia (VP)